    Reduce Wellbore Storage Time With a Downhole Shut-in

    Pressure transient testing is a form of well testing that requires a flow period followed by a shut-in period on a well. The length of shut-in time can vary significantly depending on well and reservoir parameters, such as permeability. A high-perm gas storage well may only require a 1 hour shut-in whereas a low-perm tight sandstone well may require a month-long shut-in. The longer the shut-in, the more expensive the well test and thus anything that can be done to reduce the test duration without compromising the data can be really useful and budget-friendly.

    Wellbore storage, which is the first flow phase upon shut-in, will dictate how long the shut-in must be. A well must be shut in long enough to get out of wellbore storage before any meaningful analysis to be done.

    Wellbore storage time is a function of several parameters, including permeability, wellbore fluid, and wellbore volume. While we can’t change the permeability, we can reduce the wellbore volume and thus reduce the wellbore storage time. This is where a downhole shut-in comes in play. If we use a downhole shut-in, such as a bridge plug with gauges BELOW the plug, then we essentially reduce the wellbore volume to just that volume between the plug and the reservoir. This method can greatly reduce the wellbore storage time and thus reduce the overall shut-in time, saving time and money!

    If you are curious and want more information about wellbore storage, ​check out this article on our website​.